Council Gives Timeline and Update on Water Treatment Plant 

At their recent meeting, the Yass Valley Council received a report on the Water Treatment Plant, a big issue in the Yass Valley due to recurring water quality issues. Acting CEO Nathan Cooke has also given an additional update.

According to Council’s Business Papers, a budget has been allocated for pre-design and tender management for the Yass Water Treatment Plant (WTP) Upgrade in the Operational Plan 2025-26 and for upgrades to the Yass water reticulation network funded by the adhoc election commitment fund. 

The project to prepare a Design and Business Case for the upgrade of the Yass WTP commenced in November 2019. The Housing Acceleration Fund (HAF) funded this project for $1.2M with a total commitment of $10M for the WTP Upgrade. During this project, stakeholders required that early works be carried out in advance in December 2020. 

Works included the installation of a bubble plume aeration system at the Yass Dam, upgrade of the Raw Water Pump Station (RWPS), and urgent works at the Yass WTP. Works were completed for $2.2 million, funded by HAF at the end of February 2023. The Final Business Case was endorsed by Council at its extraordinary Council meeting on 9 May 2024. An upgrade of the reticulation system is also required to ensure treated water can reach customers without being impacted by the accumulated mineral deposits in the water mains. Field work commenced on 4 February 2025 and is ongoing. 

Priority components were identified based on the Network Criticality Analysis – Yass Reticulation Network, January 2024 and will be refined following the completion of the site investigations and analysis. Investigations include survey, location of utility services, geotechnical investigations and preparation of Review of Environmental Factors (REF) where required. Design drawings (80 per cent draft) were reviewed by Council, and comments were provided on 18 July 2025. Draft REF and desktop Aboriginal Heritage Due Diligence Assessment (ADDA) were completed in June.

 Finalisation of the design and tender package is scheduled for September. Council said they will also implement minor improvement works to install valves and hydrants, and continue to trial various pipe cleaning methods available in the market, rather than direct flushing. A Steering Committee meeting with the funding agency representatives for the implementation of the project is scheduled every month, which is scheduled for 26 February.

The following activities are scheduled in the report:
• Continue Reference Design and preparation of tender documents.
• Complete design and tender documents for reticulation upgrades.
• Continue liaison with DCCEEW, funding agencies and technical advisories.
• Inform and engage with the community.

Acting CEO said, “We’re still looking at working towards the tender documentation, the finalisation of the reference designer Section 60 approvals by sort of early 2026. The construction tender and construction works will start towards the end of 2026 and then for completion by late 2028, so by November 2028.

 “It’s a highly technical design work that our consultants are currently doing for us, and then actually implement once the design is completed, and we have the approvals process completed as well. It’s then going to tender and getting a contractor who can come in and construct a working water treatment plant around one that’s currently having to provide water at the same time. It’s a bit of a dance around continuing to treat water and construct a treatment plant while they’re trying to operate at the same time.

“We’ve got the raw water pump stations that have all been mostly upgraded in the last couple of years. We purchased extra land next to the water treatment plant. We are going through the heritage and environmental assessments as we speak, working our way through that, and the design team is obviously working out what the configuration of the water treatment plant looks like on that site.

 “We’re sort of at 30% design at the moment, and we’ll sort of continue that through to 50% to 80% before we then go to tender for a designer construct contractor to finish the design, finalise the designer and then actually construct it. 

“That’s when we get to an exciting part, we actually get to see stuff happening on site. I’m looking forward to that.

“It’s long overdue. It’s been a project that’s been coming now for over 20 years, and we’ve finally got the funding to be able to deliver it, which is magic.” 

Nyssa Stadtmiller

The South West Slopes Times covers an area approximately the size of Fiji in country NSW. We look after a population of more than 50,000 people with our staff servicing 7 major towns and dozens of villages with our story telling footprint.

We offer weekly print editions at $3 a copy and we also offer digital subscriptions across 3 months $30, 6 months $60 and 12 months $120.

We are one of the last truly local independent family run newspaper businesses in the state.

Contact us today to find out how we can promote your business or organisation across our huge network by emailing ads@thetimes.net.au or by calling 0413 763 216.

If you have a news tip, lead or scoop for us please make contact as we love celebrating our communities. You can contribute articles via our South West Slopes Times website.

Share this:

Contribute your story

We are always looking for new stories to share with our readers. If you have a story you would like to share, click the 'Contribute' button.